Impact of BIM Implementation Timing on Constructability Coordination in Railway Viaduct Megaprojects

TITLE OF THE MASTER THESIS: Impact of BIM Implementation Timing on Constructability Coordination in Railway Viaduct Megaprojects

TITLE OF THE MASTER: BIM for Project and Contract Management in Construction Works

AUTHOR: Henrique Gazzinelli Cruz Garzon Viana

TUTOR: Prof.ssa Ronca

 

Large railway infrastructure projects require coordination across many engineering disciplines: civil, structural, track, electrical, mechanical, and railway systems works. Building Information Modeling (BIM) is one of the principal tools for managing that coordination. But the timing of its practical implementation, as distinct from its mere contractual existence, remains under-examined in the infrastructure BIM literature. Existing research documents a general lag behind vertical building projects. What it does not establish is whether that lag operates uniformly across a project, or unevenly between disciplines sharing the same contract.

This thesis examines that question through a single, in-depth case study: the viaduct works of Contract Package 01 (CP01) of the North-South Commuter Railway (NSCR) Project (Malolos-Tutuban), Philippines, where the author worked as a construction supervision engineer on the Engineer/General Consultant side. The evidence base is wide: the Employer’s General Specifications, BIM Execution Plan correspondence, BIM Progress Reports, Clash Detection Reports and their associated Requests for Information, Engineer Review Sheets, and the author’s own professional observation on site.

BIM was contractually mandated from the bidding stage, under the General Specifications (Section VI, Clause 121), which required model production principles, a Common Data Environment, clash detection routines, and monthly BIM output submissions. The mandate existed on paper well before it existed in practice: the BIM Execution Plan, and the modeling discipline it was meant to enforce, were only finalized and iterated after construction had already started. Within the viaduct scope, BIM was used on four documented occasions between July 2022 and February 2025, an anti-bursting bar and post-tensioning duct clash, a portal beam reconstruction at an existing pier, a drainage clarification, and an ad hoc audit. Three of the four were reactive, triggered only after a conflict or ambiguity had already surfaced through a Contractor query or a demolition. The fourth broke that pattern: the Engineer used BIM proactively, to head off an interpretive difficulty before it happened. None of the four, reactive or not, was part of a scheduled, recurring coordination process.

The Depot and Station Buildings tell a different story. There, a formal Clash Detection Report and Request for Information mechanism ran consistently from March 2022 onward, sustained for at least three years across multiple documented instances. The viaduct only entered that mechanism by accident, when one of its elements physically clashed with a station structure (drainage pipes conflicting with a station foundation wall, for example), and only when the station side initiated the process. A separate set of episodes, documented between 2024 and 2026 at the interface between the CP01 viaduct and the CP04 track and railway systems package, shows the same pattern recurring after construction: turnout positioning conflicts with structural expansion joints, and missing cast-in foundations for overhead catenary system supports, each surfacing only once the track contractor’s design had matured against an already-built structure. Independent tracked audit data from the neighboring CP02 elevated structures package points to the same within-contract pattern, under a completely different contractor’s BIM team.

The central argument this evidence supports is that the real gap here is one of institutionalization, not simple timing. The viaduct scope had the technical capability to use BIM for clash detection from an early stage, and used it repeatedly, three times reactively and once proactively. What it never had was an institutionalized, discipline-level process, the kind that governed the Depot and Station Building scopes under that same contract, the same BIM Execution Plan, and the same Common Data Environment. That distinction pushes the industry-level building-versus-infrastructure BIM adoption gap already identified in the literature a step further: the same asymmetry can appear within a single contract, between disciplines operating under identical contractual and technological conditions.

For Engineers, Contractors, and Employers on comparably structured railway megaprojects, the practical payoff is a diagnostic question: does a given discipline or scope package have an actual, assigned, repeatable coordination procedure, or is a BIM Execution Plan and a Common Data Environment simply being assumed to guarantee coordination across every scope? The case study is bounded to one viaduct scope and one vantage point, so the findings cannot claim statistical generalizability. What they offer instead is an evidence-supported account of a mechanism the wider literature suggests should operate more broadly on comparable projects.

Figure 1 – Integration between Viaduct and Station

Figure 2 – Sectional view inside the Station

Figure 3 – Integration of Viaduct and Main Traction Substation (MTS)